Skip to Content

Submarine Cable Manufacture and Delivery 

This is the 3rd edition of a blog series outlining how works are progressing. For the 1st edition, see here and for the 2nd edition, see here.

The ESB International Project Team, working on behalf of our esteemed client, the Electricity & Water Authority, Bahrain (EWA), were gifted an early present ahead of the holidays when the Hawar Island Submarine Cable Project reached a significant milestone at the end of November 2021. The appointed submarine cable manufacturer, LS Cable & System (LSC), commenced shipment of the first batch of cables and accessories for the project. This batch included two of the three submarine cables and their associated accessories.

 

Cable Manufacture and Testing Procedure 

The first shipment of the submarine cable came on foot of a contract awarded in February 2020 by the main contractor to LSC to manufacture and supply a total of 75 km of 66 kV XLPE (Cross-Linked Polyethylene) submarine cables. The order included three lengths of three core XLPE submarine cable, rated at 66 kV with a transfer capacity of 60 MVA each. Each cable was of continuous length without factory joints and with an integrated 48 Core Multimode Fibre Optic Cable. 

After the ESB International Cables Team completed a detailed design review of the cable technical specifications, the manufacturing process commenced during the summer of 2021 at the LSC-owned factory in Donghae, South Korea.  

Upon completion of the manufacturing phase, Factory Acceptance Tests (FAT) were conducted by ESB International during April/May 2021. The FAT covered a series of tests, including Type Tests and Short Circuit Tests, which would verify the quality of the proposed submarine cable system. 

 

Shortage of Vessel Availability and Vessel Charter Party 

The project was faced with a significant cable delivery challenge. The availability of suitable cable delivery vessels capable of transiting between Korea and Bahrain are few and far between due to the great demand in the market for vessels for other subsea cable projects worldwide. After a lengthy process, a dynamically positioned DP Class 2 vessel named the Willem de Vlamingh was secured for the cable transporting task. The vessel itself is designed for cable installation; however, in this case, it would be used only for cable transport and delivery. 

 

Upon the successful charter and based on the gathered information, a detailed vessel passage plan was prepared for the Willem de Vlamingh, which covered the entire voyage, using official nautical charts and available publications. Additionally, notices to mariners and radio navigation warnings were issued to the international seafaring community and key authorities. 

 

Cable Transloading Procedure 

Prior to the cable transportation from the factory to the delivery location at Khalifa Bin Salman Port in Bahrain, several actions were completed by ESB International and the appointed Marine Warranty Surveyor (MWS).  

These included: 

  • Detailed document reviews submitted by the manufacturer 
  • Subsea cable loading risk assessment 
  • Seaworthiness of the vessel check 
  • Completion of cable load-out and testing 
  • Preparation of the vessel and mobilisation of spare cable reels and auxiliary parts 
  • Sea fastening of the main deck equipment and cable carousel 

Before the cables could leave the Donghae Port, the final step required the issue of Certificates of Approval (CoA) by the Marine Warranty Survey (MWS). The CoA was required for Loadout and the Sea fastening & Sailaway of 50 km (Circuit 1 & Circuit 2) of the 66 kV XLPE submarine cable from the LS Cable Facility to the Willem de Vlamingh Vessel and from the Port of Donghae, Korea to Kalifa Bin Salman Port, Bahrain. 

 

Cable Delivery 

The cables and accessories are currently in transit and scheduled to arrive in The Kingdom of Bahrain on the 18th of December 2021. This date is significantly dependent upon weather conditions. Upon delivery of the cables in Bahrain, the cables will be transloaded from the Willem de Vlamingh vessel into two bespoke manufactured land-side cable storage baskets. This will be done under the supervision of ESB International and the Marine Warranty Surveyor. The cables and accessories will be stored until their delivery to the cable installation site are required in Q1 2022. 

 

The project continues to progress well, and any challenges to date have all been addressed by the Project Team. The arrival of the submarine cables in Bahrain will be a significant step forward for the project. 

Keep an eye on our social media pages and website for further updates as the project advances. 

This is the 3rd edition of a blog series outlining how works are progressing. For the 1st edition, see here and for the 2nd edition, see here.  

Author

Mark Mooney Mark Mooney Civil Engineer and Project Manager in Bahrain Hawar Island Submarine Cable Project, ESB International

About Mark Mooney

Mark Mooney is a level 9 qualified Civil Engineer, working as an International Engineering Consultant and Project Manager delivering electrical infrastructure projects in the Middle East Region for ESB International. Mark has a Master's (MEng) in Civil Engineering from the University of Ulster.  

Mark has recently delivered several strategic electrical infrastructure projects in the Kingdom of Bahrain, including Electrical Transmission Network diversions associated with Bahrain's New International Airport and a Subsea Power cable connection between Bahrain's Mainland and an offshore Island named Hawar Island. 

The experience ESB International brings as a utility-based consultancy to our parent company ESB, which is transitioning to a low-carbon energy future based on clean, reliable, affordable electricity, lends itself perfectly to further collaboration and knowledge sharing in the region. 

Related Articles

Photograph of a row of solar panels with mountains in the background
16 November 2021

ESB Solar Energy

Energy Insights Read More
Photograph of solar panels with wind turbines in the background
27 October 2021

Battery Energy Storage

Energy Insights Read More
Photograph of a windfarm at the top of some mountains with the sun setting behind
09 September 2021

Energy Efficiency Expertise

Energy Insights Read More

Contact Us

Dublin Office

Address
ESB International,
One Dublin Airport Central,
Dublin Airport Cloghran,
Co Dublin,
K67XF72
Phone +353 1 703 8000 +353 1 703 8000

Bahrain Office

Address
ESB International Office 1002,
Building 655 Road 3614,
Block 436,
Seef Area,
Bahrain
Phone +973 1770 8118 +973 1770 8118

Oman Office

Address
ESB International Office 206,
2nd Floor, Holiday Inn Al,
Mazoon Street South Al,
Mawaleh, Muscat P.O. Box,
P.C 118 Sultanate of Oman
Phone +973 1770 8118 +973 1770 8118