Skip to Content

The Client

The Electricity & Water Authority (EWA) in the Kingdom of Bahrain aims to provide electricity and water services at the highest level of quality and reliability to ensure sustainable development in the country and to be a best practice model for providing electricity and water services.  

To enable economic and social growth envisaged by Bahrain’s 2030 Economic Vision, EWA is committed to the delivery of ambitious and challenging transmission and distribution (T&D) development projects. 

 

The Project  

One major programme undertaken has been to strengthen the overall infrastructure and achieve expansion and reinforcement of existing 220kV and 66kV transmission & distribution networks in the Kingdom.  

As a utility-based consultant ESB International has developed, maintained and operated resilient transmission & distribution infrastructure in Ireland for nearly 100 years and internationally for close to five decades. ESB International was appointed by EWA as the consultant to deliver all four phases of this ambitious project. The overview of works completed for Phases 1 and 4 is as follows:  

Photograph of a boat statue with a decorative red and white sail. It is on some grass next to a well lit road in a city

Our Approach

  • The Client Challenges

    A high number of substations needed to be delivered in a short time, and all related 66kV & 220kV cable circuits required urgent approval and installation.

  • Project Scope

    The planning & design, procurement, construction supervision and overall project management of 220kV and 66kV transmission & distribution substations and cable projects.

Stage 1 - Studies & Design Stage

  • Project planning, including contract strategy, interfaces, and conceptual engineering  
  • Power System Studies  
  • Statutory Approvals

 

Stage 2 – Tendering Phase  

  • Prequalification of contractors  
  • Preparation of enquiry documents  
  • Tendering and contract award 

 

Stage 3 – Supervision and Contract Management  

  • Overall project & contract management (financial, progress monitoring, interfaces)  
  • Design review and approval, Factory Acceptance Testing (FAT) 
  • Supervision of site works and commissioning, including safety and security

 

What we delivered

Graphical image showing a gear and some lines and circles

The project is in the final stage of completion, with all works being delivered within budget with a continued emphasis on safety and maintaining high-quality standards.  

ESB International has ensured that this transmission & distribution development project has met internationally recognised quality, safety, and environmental standards. In addition, we collaborated with our client to mitigate commercial and technical exposure and risk throughout the project delivery lifecycle while deploying a best practice project management approach.  

The Results

Icon of a globe with a circle containing a check mark

  • 3 new 220/66 kV Bulk Supply Point (BSP) substations and all associated 220kV, 66kV power and communication cabling connections 
  • 16 new 66kV substations and all associated 66kV power and communication cabling connections 
  • 67 new 220kV and 66kV transformers and reactors 
  • 250km of 220kV & 66kV interconnecting cable feeders 

 

ESB International has a track record of delivering transmission and distribution projects worldwide. We have operated in the Middle East, and in Bahrain in particular, for nearly five decades. Key to ESB International's success on this major development project has been our utility background, understanding of the energy sector, and close collaboration with our client. We understand the challenges that face utilities because we're part of one. It's in our DNA.
Martin Gdovin, ESB International Project Manager

Related Case Studies

Photograph of a substation
malaysia

Transmission Substation Development Kulim Hi-Tech Park

Transmission & Distribution Read Case Study
Photograph of two men with their backs to the camera and looking at power lines. They are wearing hard hats and high vis vests with the ESB International logo on the back
tanzania

Tanzania Rural Electrification

Transmission & Distribution Read Case Study
Photograph of a man with his back to the camera. He is wearing a hard hat and a high vis vest with the ESB International logo on it. He is looking at some machinery
tanzania

Consultancy services for the Millennium Challenge Account–Tanzania (MCA-T)

Transmission & Distribution Read Case Study

Contact Us

Dublin Office

Address
ESB International,
One Dublin Airport Central,
Dublin Airport Cloghran,
Co Dublin,
K67XF72
Phone +353 1 703 8000 +353 1 703 8000

Bahrain Office

Address
ESB International Office 1002,
Building 655 Road 3614,
Block 436,
Seef Area,
Bahrain
Phone +973 1770 8118 +973 1770 8118

Oman Office

Address
ESB International Office 206,
2nd Floor, Holiday Inn Al,
Mazoon Street South Al,
Mawaleh, Muscat P.O. Box,
P.C 118 Sultanate of Oman
Phone +973 1770 8118 +973 1770 8118